Ernie Caldwell Boulevard - A new four-lane road from U.S. Highway 17-91 to west of U.S. Highway 27. Two of the project’s three sections to cost $57 million and be finished in 2010, with the cost and timing of the third leg to be determined.
County Road 54 - Known as Ronald Reagan Parkway, is being widened from two to four lanes from US 17-92 to U.S. Highway 27. Cost is $81 million. Phase one, currently is under construction and scheduled to be done in 2008, with phases two and three to be done 2010.
Pine Tree Trail - This will run from Ernie Caldwell Boulevard north to County Road 54. Cost to be $10 million with completion in 2010.
North Ridge Trail - A new two-lane road that will parallel U.S. 27, between Deen Still Road and Sand Mine Road. Cost, $35 million, with phase one to be completed in 2011.
Holly Hill Road - A new two-lane road that will parallel U.S. 27 on the east from just south of I-4 to the southern border of Haines City. Cost $60 million, with completion date to be determined.
FDC Grove Road - A new two lane road the will parallel U.S. 27 on the west from just south of I-4 to the southern border of Haines City. Cost $55 million, with completion date to be determined.
County Road 547 - Known as Jackson Highway, widening from two-lanes to four lanes west of U.S. 17-92. Cost to be $35 million, with completion date to be determined.